Watchdog criticises cost overruns on Ballymun scheme

The Government's spending watchdog has criticised cost overruns on the scheme to demolish and replace the Ballymun flats in north Dublin.

The Government's spending watchdog has criticised cost overruns on the scheme to demolish and replace the Ballymun flats in north Dublin.

In a report out today, the Comptroller and Auditor General says the Ballymun Regeneration Scheme was initially supposed to be completed by 2006 at a cost of €442m.

However, he says €501m has already been spent and the work is not expected to be finished until 2012.

The C&AG says the original targets were unrealistic and not properly coasted.

He also says more should be done to improve the employment prospects of local people and tackle crime and anti-social behaviour if the regeneration is to deliver the hoped-for benefits to the area.

more courts articles

Man admits killing Irish pensioner (87) on mobility scooter in London Man admits killing Irish pensioner (87) on mobility scooter in London
Former DUP leader Jeffrey Donaldson arrives at court to face sex charges Former DUP leader Jeffrey Donaldson arrives at court to face sex charges
Case against Jeffrey Donaldson to be heard in court Case against Jeffrey Donaldson to be heard in court

More in this section

A woman holding and giving a credit card to someone while using laptop computer Irish people bank and shop online at higher rate than other EU countries, report finds
Group says airline slots could see Dublin Airport cap breached by 10 million people Group says airline slots could see Dublin Airport cap breached by 10 million people
Coronavirus - Fri Oct 23, 2020 Doubt cast on claims majority of asylum seekers in Ireland had crossed border
War_map
Cookie Policy Privacy Policy Brand Safety FAQ Help Contact Us Terms and Conditions

© Examiner Echo Group Limited